What must happen before a Stop Work Order is lifted?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Stormwater Management Inspector Exam. Review with interactive practice questions, helpful hints, and detailed explanations. Ensure you're ready for success!

Before a Stop Work Order can be lifted, it is essential that all corrective measures specified in the order are completed. This ensures that any violations or issues that led to the issuance of the Stop Work Order have been addressed adequately. The primary purpose of a Stop Work Order is to protect public safety, water quality, and the environment by ensuring that construction or work activities comply with regulations and standards.

Once all corrective measures have been implemented, the project can be reassessed for compliance. Only then can the responsible authority confidently lift the Stop Work Order, allowing work to resume safely and legally. Addressing these measures is crucial for preventing future violations and ensuring that the project aligns with established stormwater management practices and regulations.

While inspections and other processes may be involved in the overall compliance check, the completion of corrective measures is a fundamental prerequisite for lifting the order.