What should be present before a construction record drawing is submitted?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Stormwater Management Inspector Exam. Review with interactive practice questions, helpful hints, and detailed explanations. Ensure you're ready for success!

A sealed and signed certification of proper installation is essential before submitting construction record drawings because it serves as a formal verification that the construction work has been completed according to the design specifications, applicable codes, and regulatory requirements. This certification typically comes from a registered professional engineer or architect who has reviewed the project to ensure that everything meets the necessary standards.

This certification not only assures compliance but also provides accountability, as it indicates that a qualified individual has overseen the work and confirms its integrity. Record drawings, which document the final as-built conditions, rely heavily on the accuracy of the construction process; thus, the certification is a critical component of the documentation.

While previous owners, completed landscape designs, and inspection reports for all completed work may provide useful context or additional information, they do not hold the same level of significance for the immediate submission of construction record drawings. The certification focuses specifically on the actual work completed, ensuring that everything meets the required standards before any further documentation is finalized.